Scheduling

Description: This quiz covers the fundamental concepts and techniques used in scheduling, a critical aspect of operations research.
Number of Questions: 15
Created by:
Tags: scheduling operations research project management
Attempted 0/15 Correct 0 Score 0

Which scheduling technique is commonly used for projects with well-defined tasks and dependencies?

  1. Critical Path Method (CPM)

  2. Program Evaluation and Review Technique (PERT)

  3. Gantt Chart

  4. Earliest Deadline First (EDF)


Correct Option: A
Explanation:

CPM is a widely used scheduling technique for projects with well-defined tasks and dependencies. It helps identify the critical path, which is the longest sequence of tasks that determines the project's overall duration.

What is the primary objective of scheduling in project management?

  1. Optimizing resource allocation

  2. Minimizing project duration

  3. Balancing workload among team members

  4. Maximizing project profit


Correct Option: B
Explanation:

The primary objective of scheduling in project management is to minimize the project's duration while considering constraints such as resource availability, task dependencies, and deadlines.

Which scheduling algorithm is suitable for real-time systems where tasks have deadlines?

  1. First-Come-First-Served (FCFS)

  2. Shortest Job First (SJF)

  3. Earliest Deadline First (EDF)

  4. Round-Robin


Correct Option: C
Explanation:

EDF is a scheduling algorithm designed for real-time systems where tasks have deadlines. It prioritizes tasks based on their deadlines, ensuring that tasks with earlier deadlines are executed first.

In a Gantt chart, what do the bars represent?

  1. Task durations

  2. Task dependencies

  3. Resource allocation

  4. Project milestones


Correct Option: A
Explanation:

In a Gantt chart, the bars represent the durations of tasks. The length of each bar corresponds to the estimated time required to complete the task.

Which scheduling technique is commonly used for job shop scheduling, where jobs have different processing times and routes?

  1. Critical Path Method (CPM)

  2. Program Evaluation and Review Technique (PERT)

  3. Gantt Chart

  4. Dispatching Rules


Correct Option: D
Explanation:

Dispatching rules are a set of heuristics used for job shop scheduling. They determine the order in which jobs are processed on each machine, considering factors such as job priority, processing time, and machine availability.

What is the primary objective of resource leveling in project scheduling?

  1. Minimizing project duration

  2. Balancing resource allocation

  3. Reducing project costs

  4. Improving project quality


Correct Option: B
Explanation:

Resource leveling aims to balance the allocation of resources across different tasks and time periods. It helps avoid resource overallocation and underallocation, ensuring that resources are utilized efficiently throughout the project.

Which scheduling technique is commonly used for scheduling tasks on a single processor?

  1. Critical Path Method (CPM)

  2. Program Evaluation and Review Technique (PERT)

  3. Gantt Chart

  4. Shortest Job First (SJF)


Correct Option: D
Explanation:

SJF is a scheduling algorithm that prioritizes shorter jobs over longer jobs. It aims to minimize the average waiting time of jobs by processing shorter jobs first.

What is the purpose of float or slack time in project scheduling?

  1. Identifying critical tasks

  2. Calculating project duration

  3. Determining task dependencies

  4. Providing flexibility in scheduling


Correct Option: D
Explanation:

Float or slack time represents the amount of time a task can be delayed without affecting the overall project duration. It provides flexibility in scheduling by allowing tasks to be rescheduled or adjusted without impacting the project's completion date.

Which scheduling technique is suitable for scheduling tasks with precedence constraints?

  1. Critical Path Method (CPM)

  2. Program Evaluation and Review Technique (PERT)

  3. Gantt Chart

  4. Earliest Deadline First (EDF)


Correct Option: A
Explanation:

CPM is a scheduling technique specifically designed for projects with precedence constraints. It identifies the critical path, which is the sequence of tasks that determines the project's overall duration, and helps optimize the project schedule.

What is the difference between deterministic and stochastic scheduling?

  1. Deterministic scheduling assumes task durations are known, while stochastic scheduling assumes task durations are uncertain.

  2. Deterministic scheduling is used for short-term planning, while stochastic scheduling is used for long-term planning.

  3. Deterministic scheduling is more complex than stochastic scheduling.

  4. Deterministic scheduling is always more accurate than stochastic scheduling.


Correct Option: A
Explanation:

The primary difference between deterministic and stochastic scheduling lies in the treatment of task durations. Deterministic scheduling assumes that task durations are known with certainty, while stochastic scheduling considers task durations as uncertain variables.

What is the role of safety time in project scheduling?

  1. To account for unforeseen delays and uncertainties

  2. To reduce the project's overall duration

  3. To increase the project's budget

  4. To improve the quality of the project's deliverables


Correct Option: A
Explanation:

Safety time is a buffer added to task durations to account for unforeseen delays and uncertainties that may arise during project execution. It helps mitigate the impact of unexpected events and ensures that the project is completed on or before the scheduled date.

Which scheduling technique is commonly used for scheduling tasks on parallel processors?

  1. Critical Path Method (CPM)

  2. Program Evaluation and Review Technique (PERT)

  3. Gantt Chart

  4. Parallel Processing Scheduling


Correct Option: D
Explanation:

Parallel Processing Scheduling is a specialized scheduling technique used for scheduling tasks on parallel processors. It considers the availability of multiple processors and assigns tasks to them in a way that optimizes the overall execution time.

What is the purpose of a precedence diagram in project scheduling?

  1. To identify the critical path of the project

  2. To determine the project's overall duration

  3. To represent the dependencies between tasks

  4. To allocate resources to tasks


Correct Option: C
Explanation:

A precedence diagram is a graphical representation of the dependencies between tasks in a project. It helps visualize the relationships among tasks and identify the tasks that must be completed before others can start.

Which scheduling technique is commonly used for scheduling tasks in a manufacturing environment?

  1. Critical Path Method (CPM)

  2. Program Evaluation and Review Technique (PERT)

  3. Gantt Chart

  4. Material Requirements Planning (MRP)


Correct Option: D
Explanation:

Material Requirements Planning (MRP) is a scheduling technique specifically designed for manufacturing environments. It helps plan and schedule the production process by considering factors such as material availability, lead times, and production capacity.

What is the primary objective of a resource-constrained project scheduling problem?

  1. Minimizing project duration

  2. Balancing resource allocation

  3. Optimizing resource utilization

  4. Reducing project costs


Correct Option: C
Explanation:

In a resource-constrained project scheduling problem, the primary objective is to optimize resource utilization by assigning tasks to resources in a way that minimizes idle time and maximizes resource productivity.