Geotechnical Construction and Earthworks

Description: This quiz covers the fundamental concepts and practices of Geotechnical Construction and Earthworks, including soil properties, site investigation, earthwork operations, and foundation engineering.
Number of Questions: 15
Created by:
Tags: geotechnical engineering soil mechanics earthworks foundation engineering
Attempted 0/15 Correct 0 Score 0

What is the primary purpose of conducting a site investigation in geotechnical construction?

  1. To determine the soil properties and subsurface conditions.

  2. To assess the environmental impact of the project.

  3. To obtain information for foundation design.

  4. To estimate the cost of the construction project.


Correct Option: A
Explanation:

A site investigation is crucial for gathering detailed information about the soil properties, stratigraphy, and groundwater conditions at the construction site, which is essential for designing safe and stable foundations and earthworks.

Which soil property is primarily responsible for its shear strength?

  1. Cohesion

  2. Friction angle

  3. Density

  4. Porosity


Correct Option:
Explanation:

The shear strength of soil is governed by both cohesion, which represents the interparticle attraction, and the friction angle, which accounts for the interlocking of soil particles.

What is the term used to describe the process of removing and transporting soil from one location to another?

  1. Excavation

  2. Compaction

  3. Grading

  4. Embankment construction


Correct Option: A
Explanation:

Excavation involves the removal of soil from a specific area, typically to create space for foundations, trenches, or other structures.

Which type of foundation is commonly used for structures subjected to uplift forces?

  1. Spread footing

  2. Pile foundation

  3. Mat foundation

  4. Raft foundation


Correct Option: B
Explanation:

Pile foundations are often employed in situations where uplift forces are anticipated, as they transfer the load to deeper, more stable soil layers.

What is the primary objective of soil compaction in earthwork operations?

  1. To increase soil strength and stability.

  2. To reduce soil permeability.

  3. To improve drainage conditions.

  4. To facilitate the growth of vegetation.


Correct Option: A
Explanation:

Compaction is performed to increase the density of soil, thereby enhancing its strength, stability, and resistance to settlement.

Which type of soil is most susceptible to liquefaction during an earthquake?

  1. Clay

  2. Silt

  3. Sand

  4. Gravel


Correct Option: C
Explanation:

Sand is particularly prone to liquefaction, especially loose, saturated sand, as it can lose its strength and behave like a fluid when subjected to strong seismic vibrations.

What is the purpose of installing a dewatering system in geotechnical construction?

  1. To lower the groundwater table.

  2. To improve soil stability.

  3. To prevent soil erosion.

  4. To facilitate excavation and construction activities.


Correct Option: A
Explanation:

Dewatering systems are employed to reduce the groundwater level, making it easier to perform excavation and construction activities in areas with high water tables.

What is the term used to describe the process of improving the engineering properties of soil through chemical or mechanical means?

  1. Soil stabilization

  2. Soil reinforcement

  3. Soil modification

  4. Soil treatment


Correct Option: A
Explanation:

Soil stabilization involves altering the soil's properties to enhance its strength, stability, and durability, often using chemical additives or mechanical techniques.

Which type of foundation is commonly used for structures in areas with expansive soils?

  1. Shallow foundation

  2. Deep foundation

  3. Floating foundation

  4. Pile foundation


Correct Option: C
Explanation:

Floating foundations are often used in regions with expansive soils, as they are designed to move with the soil, minimizing the risk of damage due to soil volume changes.

What is the primary function of a retaining wall in geotechnical construction?

  1. To support and stabilize soil slopes.

  2. To prevent soil erosion.

  3. To create a level surface for construction.

  4. To improve drainage conditions.


Correct Option: A
Explanation:

Retaining walls are primarily used to support and stabilize soil slopes, preventing collapse and ensuring the stability of the surrounding area.

Which type of soil is characterized by its ability to absorb and retain a significant amount of water?

  1. Sand

  2. Silt

  3. Clay

  4. Gravel


Correct Option: C
Explanation:

Clay soils have a high affinity for water due to their small particle size and high surface area, allowing them to absorb and retain a substantial amount of moisture.

What is the term used to describe the process of compacting soil in thin layers using specialized equipment?

  1. Tamping

  2. Rolling

  3. Grading

  4. Excavation


Correct Option: B
Explanation:

Rolling involves using heavy rollers to compact soil in thin layers, increasing its density and improving its engineering properties.

What is the primary purpose of conducting a laboratory soil test?

  1. To determine soil properties and characteristics.

  2. To assess the environmental impact of soil.

  3. To evaluate the suitability of soil for construction purposes.

  4. To estimate the cost of soil remediation.


Correct Option: A
Explanation:

Laboratory soil tests are performed to obtain detailed information about soil properties, such as grain size distribution, plasticity, and shear strength, which are crucial for geotechnical design and analysis.

Which type of foundation is commonly used for structures subjected to lateral loads?

  1. Spread footing

  2. Pile foundation

  3. Mat foundation

  4. Raft foundation


Correct Option: B
Explanation:

Pile foundations are often employed for structures subjected to lateral loads, as they provide deep anchorage and can transfer the load to stable soil layers.

What is the term used to describe the process of excavating soil to create a level surface for construction?

  1. Grading

  2. Excavation

  3. Compaction

  4. Embankment construction


Correct Option: A
Explanation:

Grading involves shaping and leveling the ground surface to prepare it for construction activities, ensuring proper drainage and stability.